Directory / Facilities / Samsung SDS AI data center, Gumi
Facility
Samsung SDS AI data center, Gumi
Observations
| Metric | Value | Unit | As of | Period | Label | Source | Notes |
|---|---|---|---|---|---|---|---|
| expandable_capacity | 120 | MW | 2026-11-02 | planned | The Korea Herald | ||
| initial_capacity | 60 | MW | 2026-11-02 | planned | The Korea Herald | Expandable to 120 MW; completion by end of 2028. | |
| investment_krw | 427,300,000,000 | KRW | 2026-11-02 | measured | The Korea Herald | ||
| investment_usd | 319,000,000 | USD | 2026-11-02 | illustrative | The Korea Herald | USD equivalent as reported. | |
| site_sqm | 46,000 | sqm | 2026-11-02 | measured | The Korea Herald |