Directory / Events / Reuters: data centers are hunting used turbines and converted jet engines as new-turbine delivery runs ~6 years in the U.S. (Nov 9)

Event

Reuters: data centers are hunting used turbines and converted jet engines as new-turbine delivery runs ~6 years in the U.S. (Nov 9)

event type
market_print
occurred on
2026-11-09

Observations

Every number below has a source. Labels mark the figure as measured, illustrative, or planned.

MetricValueUnitAs ofPeriodLabelSourceNotes
global_turbine_orders100GW2026-11-09measuredReuters via Investing.comWood Mackenzie, as reported by Reuters.
new_unit_pricenew ~$2–$2.5M/MWUSD_million_per_mw2026-11-09measuredReuters via Investing.comAurora Energy Research.
production_capacity60–70 GW of production capacityGW2026-11-09measuredReuters via Investing.comWood Mackenzie range.
refurbished_unit_price1.3USD_million_per_mw2026-11-09measuredReuters via Investing.comOrigin Partners.
us_data_center_turbine_demand17GW2026-11-09measuredReuters via Investing.comJefferies estimate.
used_unit_pricewell-maintained used units ~$1.5–$1.7M/MWUSD_million_per_mw2026-11-09measuredReuters via Investing.comOrigin Partners, as reported.

Connections

No edges in this snapshot.