Directory / Events / AI data center late fees jump to $5M+/day, and Marsh builds "delay-in-delivery" insurance (Oct 25)
Event
AI data center late fees jump to $5M+/day, and Marsh builds "delay-in-delivery" insurance (Oct 25)
- event type
- market_print
- occurred on
- 2026-10-25
Observations
| Metric | Value | Unit | As of | Period | Label | Source | Notes |
|---|---|---|---|---|---|---|---|
| late_fee_new_deals | 5,000,000 | USD_per_day | 2026-10-25 | measured | The Information via Benzinga | Asked in new deals, as reported via Benzinga syndication. | |
| late_fee_spring | 1,000,000 | USD_per_day | 2026-10-25 | measured | The Information via Benzinga | Spring example from The Information via Benzinga; the Information article itself is paywalled. |
Connections
- about → Marsh company